SHAR
Production
QC Checklist · 18/50 · audio
Programme loudness outside target QC checklist
Completion
0 / 5
01
Confirm the reported programme loudness outside target condition and identify every affected asset or task.
02
Measure integrated loudness, range and gating using the delivery standard.
03
Pause or quarantine affected outputs so the problem cannot propagate to another production stage.
04
Adjust the mix, remeasure the complete programme and retain the meter report.
05
Record the owner, evidence, decision, version and completion time in the production log.
Reset checklist